Case Study | Facility Decommission + Closeout
Seven-Day Closeout.
Three-Day Bulk Removal.
Zero Reported Damage.
ASI cleared and restored a 45,000-square-foot Panasonic facility through one controlled plan, even after field volume proved roughly 50 percent greater than anticipated.
Overview
Challenge
A compressed lease transition left one shared elevator for concurrent move and decommission activity. The facility also contained approximately 50 percent more material than the initial estimate.
ASI Approach
Validate the field condition, expand hauling capacity, coordinate material flow around shared access, recover usable furniture value, complete restoration work, and carry the facility through final review.
Results
- Bulk removal completed in three days within a seven-day full engagement
- Finished ahead of schedule and on budget
- Zero reported facility damage or incidents
The ASI Approach
From Site Walk to Turnover.
Seven Controlled Days.
As the scope expanded, ASI adjusted resources and sequencing while preserving the access, hauling, restoration, recovery, and safety controls required for closeout.
The Outcome
27 Truckloads Removed.
Value Recovered.
Facility Released Early.
The expanded scope was absorbed without extending the deadline or losing control of final condition.
Schedule Recovered
Added hauling resources and revised sequencing kept the larger field volume from extending the deadline.
Material Value Returned
Furniture resale returned a $13,000 credit, while more than 70,000 pounds of metal were separated for recycling.
Broader Scope Absorbed
Patch and paint, IDF rack removal, and specialty-disposal coordination were integrated into the field plan.
Clean Turnover
The facility reached final review ahead of schedule, on budget, and with zero reported damage.
Accelerated Closeout
Capacity Mobilized.
Facility Cleared and Restored.
The project combined high-volume material movement with closeout work that preserved the ceilings, carpet, and finished interior condition.

Truck and Container Staging
Hauling capacity was mobilized to keep 27 truckloads moving through the compressed removal window.

Active Decommission
Furniture and material were moved through a controlled hauling and recovery sequence.

Cleared Floor Ready for Review
The large open area was cleared while the carpet and finished ceiling remained intact.

Restored Interior
The completed space was cleaned and released with its finished ceiling and carpet preserved.
Project Partner Feedback
“In spite of the delays and expanded scope, ASI finished ahead of schedule, on budget, and with zero damage to the facility.”
Loren Smith
Senior Director, Cumming